DMT introduced a streamlined process in August 2025 for certain minor residential works across Abu Dhabi. The published examples include non-structural interior / exterior modifications, general maintenance and interior finishes, as well as certain other minor works. That route should not be confused with approval for structural alteration, major MEP relocation or a change of use.
For substantial interior architecture, the statutory consultant should identify the required building-permit, structural, MEP, fire / life-safety and landlord / community submissions for the specific property. DMT's Binaa platform also publishes current guidance for structural drawing submissions covering new projects, modifications and additions.
Abu Dhabi City Municipality states that privately funded projects must achieve at least a 1-Pearl Estidama rating and government-funded projects at least 2 Pearls where the Pearl Rating System applies to building-permit compliance. For existing renovation, the project's sustainability consultant should confirm which Estidama requirements actually apply instead of treating every renovation as a new-build rating exercise.
DMT's Sahel Rating System is integrated across design, construction and operation. DMT states that the mandatory system first applies to new developments, and the Sahel Building Rating System handbook also provides a route for redevelopment and renovation projects. Accessibility therefore belongs in the spatial concept, not as a final furniture check.
DMT's Building Occupancy and Legalisation Certificate Programme is also being actively enforced in 2026. An occupancy certificate certifies that a building is secure for use and complies with applicable standards; major renovation should therefore be coordinated with the legal status and approved condition of the existing property.
Bella develops the interior architectural design intent and coordinates the client-facing design decisions. Where the law or project requires an architect, structural engineer, MEP engineer, fire consultant or registered submitting consultant, those parties retain their statutory design, calculation, submission and certification responsibilities.
- Obtain existing approved architectural / structural / MEP information where available
- Confirm landlord / community NOC and fit-out requirements
- Classify proposed walls / openings before demolition
- Confirm structural-engineer scope for structural intervention
- Confirm DMT / Binaa permit route through the statutory consultant
- Coordinate MEP changes before wet areas or ceilings are fixed
- Coordinate Civil Defence / fire-life-safety requirements where applicable
- Confirm Sahel / accessibility obligations for the project
- Confirm Estidama applicability and target with the sustainability consultant
- Check existing occupancy / legalisation status where relevant
- Do not begin structural demolition from an interior concept drawing alone
Read the current Abu Dhabi Department of Municipalities and Transport — Minor Works Permit Process ↗