Dubai Department of Economy and Tourism (DET) manages hotel licensing, inspection and classification. DET's current hotel-classification service states that all hotels must apply for classification to operate in Dubai. The application requires items including DET initial approval and a Dubai Municipality building completion certificate, followed by a DET site inspection.
Hotel classification is not a substitute for building and fit-out approvals. The project still has to follow the applicable building authority, fire / life-safety, utility, landlord / free-zone and operator requirements.
For restaurants, cafés and other food establishments, Dubai Municipality publishes the Dubai Food Code and activity-based Food Establishment Requirements. Kitchen, food preparation, storage, sanitation and related technical layouts should be developed around the current activity requirements rather than generic restaurant planning ratios.
Dubai Civil Defence approval applies to fire and life-safety systems as required by the project: fire alarm, sprinklers, emergency lighting, egress and the relevant material / assembly performance. We coordinate decorative ceilings, partitions, lighting and finishes around the approved fire strategy instead of treating DCD systems as items to hide later.
Where Dubai Development Authority is the relevant jurisdiction, the current DDA Fit-Out Permit fee is AED 0.90 per ft² with a minimum AED 200 and maximum AED 10,000, plus Knowledge and Innovation Dirham charges. The service requires items including tenant contractor appointment, EJARI, building-owner NOC, authority NOCs and drawings. DDA requires a DCD Completion Certificate before the Fit-Out Completion Certificate.
Projects in malls, DIFC, TECOM-related districts, hotel compounds and mixed-use developments can also have landlord design reviews, delivery booking, work-hour, hoarding, signage and service-lift rules. These project-specific conditions often control programme as much as statutory review.
DEWA coordination may be required where electrical or water loads change materially. Restaurants, bars, laundries, spas, commercial kitchens and large decorative-lighting schemes can add substantial loads compared with a standard retail or office shell.
Bella coordinates the hospitality interior-design package with the licensed architect, MEP, fire, structural, kitchen / food-service and other consultants responsible for statutory submissions. The exact authority matrix is confirmed after the address, building and hospitality activity are known.
- Confirm exact Dubai jurisdiction / free zone
- Confirm DET hotel category where applicable
- Confirm landlord / operator design guidelines
- Confirm food-establishment activity for F&B
- Confirm kitchen / extraction route
- Confirm DCD fire strategy
- Confirm electrical and water loads
- Confirm DDA / DM / free-zone permit route
- Confirm accessible routes and guest facilities
- Confirm loading / service-lift logistics
- Confirm signage / façade rules
- Confirm work-hour restrictions
- Confirm prototype / mock-up requirements
- Track material fire / performance submittals
- Complete commissioning
- Complete fit-out / authority close-out
- Complete hotel classification / inspection where applicable